REMIT-Compliance
23. April 2026
FAQ: ACER REMIT Reporting
Which fundamental data reports may be required for a photovoltaic park?
Electricity Rights
-
- This report concerns rights for access to grid capacities and is generally used for larger networks or capacities.
- E.g. for a 10 MW photovoltaic park, this report is usually not required unless the park needs to acquire or transfer rights related to grid capacity.
- This report concerns rights for access to grid capacities and is generally used for larger networks or capacities.
Electricity Bids
-
- This report pertains to bids made on the electricity market.
- E.g. if the photovoltaic park is directly feeding into the market and placing bids, this report is required.
- This report pertains to bids made on the electricity market.
Electricity Total Allocation
-
- This report concerns the allocation of electricity and is used for distribution of generated amounts.
- E.g. if the photovoltaic park is part of a system where allocations are given (e.g., in FiT contracts or market mechanisms), this report is required.
- This report concerns the allocation of electricity and is used for distribution of generated amounts.
Electricity Nominations
-
- This report concerns the nominated amount of electricity scheduled for delivery.
- E.g. if the photovoltaic park nominates how much electricity it will deliver, this report is required.
- This report concerns the nominated amount of electricity scheduled for delivery.
Electricity Configuration
-
- This report concerns changes in the system configuration of generation plants or networks.
- E.g. for a 10 MW photovoltaic park, this report would be required if there are changes to the setup of the park or grid infrastructure, such as during construction or major maintenance.
- This report concerns changes in the system configuration of generation plants or networks.
Electricity Generation Load
-
- This report concerns the generation load and should be submitted if the amount of electricity generated changes or if there is a significant deviation from the expected load.
- E.g. for a 10 MW photovoltaic park, this report is required if there is a significant change in the generated electricity, such as due to unexpected outages or changes in solar conditions.
- This report concerns the generation load and should be submitted if the amount of electricity generated changes or if there is a significant deviation from the expected load.
Electricity Outage
-
- This report concerns outages of power generation plants or networks.
- E.g. for a 10 MW photovoltaic park, this report is required if there is an outage of the facility (e.g., technical failure or unexpected shutdown of generation).
- This report concerns outages of power generation plants or networks.
Electricity Publications
-
- This report concerns the publication of market-relevant information.
- E.g. for a 10 MW photovoltaic park, this report may be required if the park publishes market-related data (e.g., publicly available information about production).
- This report concerns the publication of market-relevant information.